← News archive

Power · NEWS BRIEF

Norway pauses new data center grid reservations

Statnett’s main office building in Oslo, photographed in 2020.
Photo: Olav Helland, “Statnett main office,” CC BY-SA 4.0; the operator’s Oslo office in 2020, resized and converted. · CC BY-SA 4.0 licence

Published

A pause on new reservations

Norway’s transmission system operator Statnett says it is temporarily stopping additional grid-capacity reservations for data centers. It expects the pause to be lifted no later than August 1, 2027, as it develops technical requirements for connecting large loads.

Statnett is also pausing review of new applications for approval of facility functionality, as well as already received applications for facilities connecting directly to the 420-kilovolt grid. The operator says existing connections are unaffected, and facilities with the necessary functional requirements already approved can still connect.

Source: Statnett announcement — November 9, 2026 ·

What the queue numbers represent

Statnett reports 800 megawatts of data-center load already connected, 4,200 megawatts with reserved capacity, and 9,100 megawatts in a capacity queue. It says inquiries cover a further 18,000 megawatts. These are different stages of the connection process, not a count of completed data centers or new power plants.

A reservation identifies grid capacity for a proposed connection; a queued request is still waiting for available capacity. Neither figure means the full amount is already being consumed. The operator says it will not assign capacity to other customers in a way that disadvantages data centers ahead of them in the queue.

Why the operator wants new rules

Statnett says data centers can change their electricity demand quickly, use software-controlled loads and be vulnerable to grid disturbances. Its concern is how those characteristics interact with stable operation of the power system as more large sites connect.

The operator gives examples of possible requirements: when a data center should remain connected during a disturbance, how quickly its consumption can change, and measures to reduce the risk of oscillations. Those examples describe requirements being developed, not final rules already approved.

What happens next

Some applications already under review for near-term connections to regional grids will continue, Statnett says, and it may consider some smaller facilities planning to connect before August 2027. The proposed requirements will go through consultation and need approval by Norway’s energy regulator, RME.

The stated August 2027 date is the operator’s expectation, not a commissioning date for a particular project. Statnett says it will discuss the decision with affected customers and grid companies while the technical requirements are developed.

Understand the infrastructure

How a data center gets connected to the grid

Sources linked below.